Welcome to The Cruden Bay Golf Links Maintenance Blog.

Monday, 16 April 2012

Spring Dressings

Today we have managed to get our 5th Top Dressing of the Season on our Greens : )
Topdressing helps to promote smooth / true surfaces, it also helps dilute any thatch build up, and helps percolation/drainage its a win win win situation ! 

Monday, 9 April 2012

Soil Screening

We have just taken delivery of our new Soil Screener  :  )

This will allow us to be self sufficient in mixing our own soils ,top dressing and divot mix on site using recycled waste from refacing old bunkers,grass clippings turfing jobs ect.


Wednesday, 7 March 2012

Putting/Chipping Area Gets Major Refurbishment



The last big job this winter is to completley overhaul the Putting/Chipping Area between the Pavillion and the Driving Range.We are extending the putting area to create a putting course , filling in the old practice bunkers and building a new one in a safer location.The aim is to make this area a safer and more enjoyable place to practice Putting,Chipping and Bunker Play.
Old Worn Out Bunker


Filled in 2/3 of it and Shaped a Grass Hollow to mimic lots of on course situations!




                       To allow us to extend the Green this old Ridge was removed.
                                                         Turfing Away

                              New Practice Bunker Under Construction.                                                       

Tuesday, 21 February 2012

Turf Nursery

We have just completed the construction  of a brand new turf nursery,its a big step forward for us as we will no longer have to rely on using the turf from the practice chipping green .

Monday, 13 February 2012

February Update

The weather over the last few weeks has been great for getting work done .

The 7th Tee is now completed with just Irrigation Heads to fit.
Relevelled walkay to the 7th fairway is being Turfed .

Verti Draining Fairways has begun with 3/4 inch Tines to a depth of 9 inches.

A new work bench for setting up cutting units is being constructed ,with no black thumbs being reported yet !

Construction of a new Greens Turf Nursery is going well .Irrigation feed has been ploughed in. Most of the groundworks have been completed just final shaping left to do and were ready for the turf to arrive .

Tuesday, 10 January 2012

Winter Aeration

                                                              The 4th  Port Erroll

 The Storms from last week have passed so we are using the good weather to get some aeration done :  )
All Greens Will Be Verti Drained with 1/2 inch Tines to a Depth of 8 Inches.

Work Continues on the 18 th surround the Rear of the Green and LHS have been Turfed ,this leaves the RHS to be shaped prepped and turfed.
This is our 1st post of 2012 so we wish all our followers a Happy New Year !

Friday, 16 December 2011

18th surround

We have been busy during the last few weeks working on improving the area around the 18th green.  Previously, the whins had encroached to such a degree that a ball missing the green by only a few yards would often end up lost or unplayable.  An area of whins were dug out, the area landscaped, marram transplanted and turf laid.  There are now new interesting run-off areas giving the golfer several options should they miss the green.
 
Hard at it!

Through the back

Prepped and ready for turf.


The high winds of last week created a few problems for us.  Several round bales from the neighbouring farmland found their way down to the right hand side of the 12th hole.
New hazards at 12th